Myers SCADA Upgrades

Construction Projects

H.E. Myers Water Treatment Plant


January 2026 - We are now officially entering the construction phase of the Myers SCADA & Electronic Security Upgrades Project. EP Breaux crews are on site and have begun installing conduit. Wire pulling and hardware installation will begin in the next coming weeks. 


January 2026 - We are now officially entering the construction phase of the Myers SCADA & Electronic Security Upgrades Project. EP Breaux crews are on site and have begun installing conduit. Wire pulling and hardware installation will begin in the next coming weeks. 


January 2026 - We are now officially entering the construction phase of the Myers SCADA & Electronic Security Upgrades Project. EP Breaux crews are on site and have begun installing conduit. Wire pulling and hardware installation will begin in the next coming weeks.
 

The new floor for the Myers Control Room
April 2026 - The floor of the Control Room has been newly renovated.

More renovated walls and flooring in the Control Room
April 2026 - Additional walls and flooring have also been recently renovated.

The new security panel in the IT closet
April 2026 - A new security panel has been installed in the IT closet with a fireproof backer board which will be painted to match the wall.

A camera box and wire cable pulled into the filter gallery
April 2026 - A camera box wire cable has been pulled into the filter gallery.

A new conduit in the sludge building with cables pulled
April 2026 - A new conduit has been installed in the sludge building with cables pulled.


April 2026 - New security cameras installed at the filters as well as the Sludge building. Card Reader wiring has also been installed.


April 2026 - New security cameras installed at the filters as well as the Sludge building. Card Reader wiring has also been installed.


April 2026 - New security cameras installed at the filters as well as the Sludge building. Card Reader wiring has also been installed.


April 2026 - New security cameras installed at the filters as well as the Sludge building. Card Reader wiring has also been installed.


April 2026 - New security cameras installed at the filters as well as the Sludge building. Card Reader wiring has also been installed.


April 2026 - New security cameras installed at the filters as well as the Sludge building. Card Reader wiring has also been installed.

Today's Hours

Call Center: 8:00AM - 5:00PM

24-hour drive-thru and walk-up kiosks at old Wells Fargo Bank at Park Forest

Find Locations

Emergencies 24/7/365

251.694.3165

Main Office Address

MAWSS Park Forest Plaza
4725 Moffett Road
Mobile, AL 36618