Skip to main content

Projects

MAWSS has many construction projects and other capital improvement projects. From repairs to new expansions of infrastructure and more, check here for a list of current and upcoming projects.

Capital Projects

Eslava Creek 48" Forcemain Sliplining

Ends: Dec 31st, 2025

MAWSS is rehabilitating a 48" wastewater forcemain by Eslava Creek via sliplining. The involves installing a slightly smaller carrier pipe into the forcemain.Estimated Cost: $4,256,208.00Estimated Completion: December 2025.

View

Construction Projects

C.C. Williams Wastewater Treatment Plant Dewatering Facility

Ends: Dec 31st, 2099

A new sludge dewatering facility is being constructed at the C.C. Williams Wastewater Treatment Plant. The new facility will have greater capacity, reliability and efficiency than the existing older facility. Increased dewatering efficiency means reduced costs in hauling sludge. Sludge from both the

View

Capital Projects

Stickney Water Treatment Plant Electrical Upgrades

Ends: Dec 31st, 2099

The E.M. Stickney Water Treatment Plant, initially constructed in 1942 and is Mobile's primary drinking water treatment facility, will be getting a complete overhaul of all electrical systems. This project includes the installation of new generators providing greater electrical capacity and

View

Construction Projects

Magnolia Grove Lift Station & Force Main

Ends: Dec 31st, 2099

The Magnolia Grove Lift Station and Force Main is being constructed to reduce sanitary sewer overflows (SSOs) in the area resulting from blockages in the long gravity sewer crossing under the golf course.The project started on April 11, 2022.The anticipated completion date is May 6,

View

Capital Projects

Stickney Water Treatment Plant 50 Million Gallon Reservoir Rehabilitation

Ends: Dec 31st, 2099

MAWSS is rehabilitating the 50 million gallon reservoir at the E.M. Stickney Water Treatment Plant.Start Date: May 23, 2023Completion Date: May 19, 2025Cost: $13.9 Million

View

Construction Projects

Mobile St LS051 Forcemain Upgrade

Ends: Dec 31st, 2099

This project is to redirect LS051 flow through a larger carrier pipe and different discharge point to help mitigate wet weather SSO's. Project #: 1025625Cost: $1,342,041Estimated Completion Date: June 26, 2024Click on the map to the right to view a

View

Construction Projects

Baker LS089 to Augusta LS189 Forcemain Upgrade

Ends: Dec 31st, 2099

This project is to redirect LS089 flow through a larger carrier pipe and different discharge point at LS189 to help mitigate wet weather SSO's. Project Cost: $1,353,250.00Estimated Completion Date: May 2024

View

Capital Projects

Eslava Creek Trunk Sewer Upgrades

Ends: Dec 31st, 2099

A new trunk sewer is being constructed parallel to the existing Eslava Creek trunk sewer for the purpose of reducing wet weather SSOs along the Eslava Creek trunk sewer. The new pipeline will add capacity for conveying wastewater from near Mt. Island Drive to a new pump station at Bucker Rd. The

View

Capital Projects

Norton's Lane Severe Weather Attenuation Facility

Ends: Dec 31st, 2099

Two 10 million gallon tanks will be constructed south of Norton's Lane and east of Navco Road to alleviate wet weather SSOs that occur near the Eslava Creek Trunk Sewer. The facility will also include a pump station constructed at 1272 Bucker Rd.Cost of Project:

View

ARCGIS Map of all Capital Projects

Today's Hours

Call Center: 8:00AM - 5:00PM

Lobby Hours (Kiosk Only): 8:00AM - 4:30PM

Find Locations

Emergencies 24/7/365

251.694.3165

Main Office Address

MAWSS Park Forest Plaza
4725 Moffett Road
Mobile, AL 36618